Wacker Neuson WL 30 Betreibershandbuch Seite 226

  • Herunterladen
  • Zu meinen Handbüchern hinzufügen
  • Drucken
  • Seite
    / 246
  • Inhaltsverzeichnis
  • LESEZEICHEN
  • Bewertet. / 5. Basierend auf Kundenbewertungen
Seitenansicht 225
S A F E T Y I NS T R U C TI O N S F O R R EPA I R S
224
Before performing welding work on the loader
Disconnect the battery as described in this Operators
Manual.
Disconnect the positive pole (terminal B+) on the gen-
erator.
Switch OFF the battery disconnect switch (if present).
Protect bare terminals and connections against short-
circuiting.
Attach the welding grounding terminal in the immedi-
ate vicinity of the welding site. Do not allow the welding
current to pass through gears, bolts, articulated joints
or hydraulic cylinders.
After welding has been completed:
Reconnect all the electrical connections and check that
they function.
Connect the battery as described in this Operators
Manual.
Seitenansicht 225
1 2 ... 221 222 223 224 225 226 227 228 229 230 231 ... 245 246

Kommentare zu diesen Handbüchern

Николай 26 Nov 2024 | 09:45:32

Назначение плавких предохранителей